Self Service 9

5%

Status

In Process [In Process]

5% complete, updated on Thu 4/17/25 7:40 AM by Douglas Austin

Changed Health from Red - At risk with no corrective actions to Green - On track.
Starting to have end users test their modules starting with Financial Aid. OIT is going throw all the modules and making setup changes and fixing any broken links that we are able to find.

Details

Dates
Fri 1/13/23 - Sat 1/13/24
Acct/Dept
Office of Information Technology
Service
Project Requests / IT Project Request
Type
Projects / IT Project
Health
Green - On track
Portfolio(s)
Classification
Upgrade
Created
Fri 1/13/23 2:01 PM
Modified
Thu 4/17/25 7:41 AM
Desired Completion Date
Please provide the estimated date for project completion.
01/15/2024
Justification
This section should contain the reason for the project and a description of the benefits to your office and the university.
Ellucian is going "end of life" soon.
Number of Departments
More than 6

Description

Implementation of Self Service 9 to replace our current Self Service 8 environment.

Manager

Alternate Manager(s)

Sponsor