Self Service 9

95%

Status

In Process [In Process]

95% complete, updated on Mon 11/10/25 2:46 PM by Douglas Austin

Changed Percent Complete from 90% to 95%.
Changed Health from Red - At risk with no corrective actions to Green - On track.
Continuing to work on custom forms that still exist.

Details

Dates
Wed 1/1/25 - Wed 10/1/25
Acct/Dept
Office of Information Technology
Service
Project Requests / IT Project Request
Type
Projects / IT Project
Health
Green - On track
Portfolio(s)
Classification
Upgrade
Created
Fri 1/13/23 2:01 PM
Modified
Mon 11/10/25 2:46 PM
Desired Completion Date
Please provide the estimated date for project completion.
01/15/2024
Justification
This section should contain the reason for the project and a description of the benefits to your office and the university.
Ellucian is going "end of life" soon.
Number of Departments
More than 6

Description

Implementation of Self Service 9 to replace our current Self Service 8 environment.

Manager

Alternate Manager(s)

Sponsor